Central Trail Update – Great News

image

Well, it’s been over a month since the Ribbon Cutting on June 2, and now it looks like the Central Trail (southern extension) is almost complete. It seem like we went weeks with no progress on the few remaining gaps. Now, all that’s left are a few curb finishes, where it crosses Polk Street.

image

There is also some great news with the trail extension, just north of Arapaho Road. The ‘bonus’ connection to the DART Arapaho station is really taking shape. The forms are up and you can see the full length of that section.

image

For those of you wondering how they intend to connect the trail to the train platform, that mystery has been answered. They are installing a small bridge that goes over the sub-Greenville Avenue tunnel ramp. Now you can connect directly from the trail to the Aprapho Station platform without having to cross to the entrance on the other side of Greenville.

image

Filed under: Bike Change, Bike Trails and Routes, City Stuff, , , , , , ,

Central Trail Nearing Completion

CentralTrailMap

According to last week’s city newsletter “Week In Review”, the Central Trail extension is nearing completion:

The expansion of the Central Trail is about 90 percent complete, and the City plans to celebrate its grand opening with a ribbon cutting June 2. The 1.9-mile southern expansion connects the 10-foot wide multiuse trail from the Arapaho Road DART Station to Richardson’s southern city limit. A future connection in the City of Dallas is expected to eventually tie it into the White Rock Creek Trail. The $4.5 million project is funded through Dallas County, $1.4 million from the City of Richardson’s 2010 Bond Program and Regional Tollway Revenue funds. 

The City is also working to expand the Central Trail half a mile to the north to Richardson’s northern city limit. The existing trail ends at Renner Road, but the expansion will tie in to the CityLine development and eventually connect to the Plano trail system. The $1.8 million northern expansion is funded through Regional Tollway Revenue and the City’s Tax Increment Finance Zone #2. It is expected to be complete in the summer of 2015 and will allow the trail to run from city limit to city limit. 

Watch a City Council work session presentation about progress on the Central Trail at bit.ly/1lDwyxu

We can’t wait to ride this. It’ll be fantastic once cyclists are able to ride from the north end of town, eventually to the White Rock Creek Trail and into Dallas.

 

Filed under: Bike Trails and Routes, City Stuff, , , , , ,

More Progress On Central Trail South

Central Trail South

This section is heading south to Spring Valley Station.

We’ve been following the progress on the Central Trail South (what we are calling the DART Trail section between Arapaho Road and 635 LBJ) and we are seeing some great progress. The last time we checked, the biggest barrier – which was building the trail over some creeks and drainage systems (between Belt Line Road and Spring Valley Road) – was requiring some major, time consuming construction.

From our latest inspection over the past weekend, we discovered that most of that construction is complete. All that remains, of the full trail extension, are just a few small pockets of missing trail, as well as the final, finishing touches. We’re hoping these are finished soon.

Central Trail South

This section is covering the new drainage systems.

We’ve also discovered a new addition to the Central Trail south – trail construction NORTH of Arapaho. You may remember us pointing out the ‘gap’ in the original plans for the trail extension, back in 2010. We were concerned that the connection to the south extension was nothing more than a narrow sidewalk. We are glad that this issue was addressed and they are now continuing the wider trail from Arapaho Road, all the way to Arapaho Station. We would love to see that gap eventually connect to the north part of the Central Trail.

Central Trail Connection

This is the new section north of Arapaho Road.

Filed under: Bike Change, Bike Trails and Routes, City Stuff, , , , ,

Richardson City Council Awards Bid for Central Trail Construction

End Bike Route - Red Line

 

From the City of Richardson weekly newsletter:

The City Council on Monday awarded a bid of $3.4 million to Ed Bell Construction Company to extend the Central Trail 1.9 miles from the Arapaho Road DART Station to the southern city limit. Construction of the 10-foot wide concrete multiuse trail is expected to begin in April and last for about one year. 

The $4 million project is funded through Dallas County and the City of Richardson’s 2010 Bond Program. The lowest bid to construct the trail came in about $400,000 over budget, so the City removed some amenities such as irrigation systems, landscaping, and benches to be constructed in a possible second phase at a future date. The City also hopes to use $600,000 in Regional Tollway Revenue funds awarded for the Central Trail to help enhance the project. 

The Central Trail currently runs from the Spring Creek Trail in north Richardson and ends at the Arapaho Road DART Station. The extension will run alongside the DART rail line and is planned to eventually connect with the Richardson city limit to the south and a future connection to the Dallas’ White Rock Creek Trail

Watch the City Council presentation at http://bit.ly/V6oiYQ.

We are extremely excited that this is happening and we’d still like to see the small gap in the plan addressed.

Filed under: Bike Change, Bike Trails and Routes, City Stuff, , , , , , , , ,

Find Us

Enter your email address to subscribe to this blog and receive notifications of new posts by email.

Join 1,356 other followers

Share This Blog

Facebook Twitter More...


Get Your BFR Swag Here!

BFR on Flickr

More Photos

HOME









Retail Partners





Richardson Bike Shops

Richardson Bike Mart

The Bike Shop

FRIENDS

Suburban Assault
Biking In Dallas
Bike DFW
Bike Texas
League of American Bicyclists
Dallas Off Road Bicycle Association
DART
streetsblog.net
Transportation for America Coalition
People For Bikes

Bike Friendly Oak Cliff


Bike Denton














Bike DFW
Also In New Zealand

Texas Bicycle Accident Lawyer

Contributors

Follow

Get every new post delivered to your Inbox.

Join 1,356 other followers