A bunch has happened since our last report on the almost completion of the first Central Expressway underpass , just south of Renner Road.
It now appears that the second Central underpass, just north of Renner Road, has been poured as well. That portion of the Richardson trail – from Alma Road (at the PGB Tollway), running under Central Expressway, then around to Renner Road – is complete.
The underpass at Renner Road – connecting this new trail to the existing Spring Creek Trail – is all that is left. As of a few weeks ago, it still looked like there was plenty of work that needed to be done. This weekend, we discovered that quite a bit of progress has happened and that underpass is well on it’s way towards completion.
Check out the pics:
.
Here’s a map for this section of trail:
Follow our coverage of the Spring Creek Trail extension
– Including Under Central Connections:
Trail Construction – 03/11/2010
Under Construction-Two Bike Trails Under Central Expressway – 04/03/2010
More Trail Construction Pics – 05/08/2010
Trail Construction Moving Forward Nicely – 06/13/2010
Trail Construction Update Pics – 07/25/2010
More Trail Progress – 08/21/2010
New Guard Rail – 08/28/2010
More Trail Progress – Towards The Central Underpass – 09/26/2010
Central Underpass – Progress On The West Side – 11/28/2010
More Trail Progress – Retaining Walls Under US75 – 12/05/2010
Trail Under Central Progress – More Gabion Walls – 02/13/2011
Trail Under Central Progress – West Side Ramp – 03/06/2011
Spring Creek Trail: North Of Renner Road – A Progress Report – 04/02/2011
Trail Under Central – Serious Progress – 04/17/2011
Took A Ride Under Central Expressway Today – 04/23/2011
Took A Ride Under Central Expressway Today
It isn’t finished yet, but the underpass just south of Renner Road is now paved. Hopefully, it will be open soon.
Here are some pics and a quick video:
Follow our coverage of this trail construction:
November 28, 2010
September 26, 2010
August 28, 2010
August 21, 2010
July 25, 2010
June 13, 2010
May 8, 2010
April 3, 2010
March 11, 2010
December 5, 2010
February 13, 2011
March 6, 2011
April 2, 2011
April 17, 2011
Comments Off on Took A Ride Under Central Expressway Today
Trail Under Central – Serious Progress
Looks like the forms are up on the southern underpass (just south of Renner Road). It usually doesn’t take them long to pour the slab once it’s at this point. That doesn’t mean the trail will be open, yet. There is a bunch of finishing work that needs to be done before it will be open for riders. We’ll keep you posted.
I didn’t get a chance to check the northern underpass (just north of Renner Road) – but until the Renner Road underpass is complete, that section is far from useful.
Follow our coverage of this trail construction:
November 28, 2010
September 26, 2010
August 28, 2010
August 21, 2010
July 25, 2010
June 13, 2010
May 8, 2010
April 3, 2010
March 11, 2010
December 5, 2010
February 13, 2011
March 6, 2011
April 2, 2011
Comments Off on Trail Under Central – Serious Progress
Trail Under Central Progress – More Gabion Walls
Not much to report today. With all of the bad rain and ice/snow storms this winter, I’m quite impressed with the amount of progress that has been made. That being said, we’re still a long way before completion. Hopefully, we’ll have a nice passage by the end of spring or early summer.
For now, check out these picks of the gabion wall progress.
Follow our coverage of this trail construction:
November 28, 2010
September 26, 2010
August 28, 2010
August 21, 2010
July 25, 2010
June 13, 2010
May 8, 2010
April 3, 2010
March 11, 2010
December 5, 2010
Comments Off on Trail Under Central Progress – More Gabion Walls
Comments Off on Updates To The Central Expressway and Renner Road Underpasses