Richardson City Council Approves Resolution for Work on New Trails
From last week’s city newsletter: The City Council on Monday approved a resolution that advances the development of a trail system near the future State Farm campus and surrounding area. The resolution authorizes BCS West Land Investments to design and construct the trail along Routh Creek Parkway from Renner Road to the nearby DART rail…
-
Trail Under Renner Road Is Complete
The trail under Renner Road is finally complete (although not officially opened). Check out the video from the north side to the south: [youtube=http://www.youtube.com/watch?v=74PdgiUmdTw]
-
Trail Under Renner Progress – Forms Are Up, Cement Is Being Poured
It’s been a couple of weeks since our last progress report. The city is finally getting close to completing the trail under Renner Road. All of the forms are up and they’ve started pouring the concrete on the north side. What’s interesting about this part of the process, compared to when they worked on the…
-
Major Progress With The Trail Under Renner Road
It’s been a few weeks since we reported on the Spring Creek Trail construction under Renner Road. When we checked on Labor Day, they had started to back-fill the area inside of the retaining wall. But, last week, it actually looked like some of that was dug back up. This week, however, the underpass looks…
-
Spring Creek Trail: North Of Renner Road – A Progress Report
Do you remember when Bob reported about this trail over a year ago? Back then it was just an open field and a plan to extend the Spring Creek Trail from the Renner Road at Central Expressway rest stop to Alma Road at the PGB Tollway. We’re happy to report that, over a year later,…
-
More Trail Progress
It’s amazing what could happen in a week. They had the forms set up last weekend for the addition to the trail at Renner Road and Central. This week we have about 70-80 yards of hike and bike trail, leading us closer to the pass under Central. Check back and we’ll keep you posted with…