A bunch has happened since our last report on the almost completion of the first Central Expressway underpass , just south of Renner Road.
It now appears that the second Central underpass, just north of Renner Road, has been poured as well. That portion of the Richardson trail – from Alma Road (at the PGB Tollway), running under Central Expressway, then around to Renner Road – is complete.
The underpass at Renner Road – connecting this new trail to the existing Spring Creek Trail – is all that is left. As of a few weeks ago, it still looked like there was plenty of work that needed to be done. This weekend, we discovered that quite a bit of progress has happened and that underpass is well on it’s way towards completion.
Check out the pics:
.
Here’s a map for this section of trail:
Follow our coverage of the Spring Creek Trail extension
– Including Under Central Connections:
Trail Construction – 03/11/2010
Under Construction-Two Bike Trails Under Central Expressway – 04/03/2010
More Trail Construction Pics – 05/08/2010
Trail Construction Moving Forward Nicely – 06/13/2010
Trail Construction Update Pics – 07/25/2010
More Trail Progress – 08/21/2010
New Guard Rail – 08/28/2010
More Trail Progress – Towards The Central Underpass – 09/26/2010
Central Underpass – Progress On The West Side – 11/28/2010
More Trail Progress – Retaining Walls Under US75 – 12/05/2010
Trail Under Central Progress – More Gabion Walls – 02/13/2011
Trail Under Central Progress – West Side Ramp – 03/06/2011
Spring Creek Trail: North Of Renner Road – A Progress Report – 04/02/2011
Trail Under Central – Serious Progress – 04/17/2011
Took A Ride Under Central Expressway Today – 04/23/2011